Phase 3 (2 or more months), also known as construction documents phase, takes all the decisions and testing we have done and converts them into the technical drawings needed for final pricing and permits. This is where the details get detailed and the drawing set grows rapidly. We cut wall sections and building sections through the building to figure out all the unique details in the home.

We work out the site layout to locate the house on your property. We show the locations determined by the soils engineer for the septic field and potential location of the well. The driveway and sidewalks are designed and materials selected. Sometimes we also engage a landscape designer during this phase to create an integrated design that fits the site.

During phase 3 we also do the math to size the joists, beams, and headers. The footings and wall sizes are determined and waterproofing and insulation identified. The level of detail for interiors depends on the job, but typically all the cabinets are detailed, and any unique interior feature is designed. If there is a 3D model, then this phase includes walking through showing furniture and wall art. It allows our clients to experience the home before final approvals and permit drawings are delivered to the builder.

At the conclusion of this phase the builder will send permit drawings to their subcontractors to determine contract price. This process alone can take more than a month.

Aimee doing a site measure.

Once the contract between the builder and you are signed, the permit review process begins in the local jurisdiction. We expect that the local building code official will issue comments during this phase that will require discussion or comments. This review process usually takes between 4 – 8 weeks. Once we satisfy all their concerns a building permit is issued and construction can begin. Navigating specific HOA or ARB requirements early is critical, as they can drastically impact the final design.

Related Posts

Thinking of Building a Luxury Home in Central Virginia? (Part 5 of 5)

Thinking of Building a Luxury Home in Central Virginia? (Part 5 of 5)

Phase 4, known as construction administration, starts with dirt moving as construction begins. We stay available ...
First Fridays At The Depot Featuring Rachel Bernstein!

First Fridays At The Depot Featuring Rachel Bernstein!

As always, this event is free and open to everyone, and refreshments will be provided by Gaines Group ...
Thinking of Building a Luxury Home in Central Virginia? (Part 3 of 5)

Thinking of Building a Luxury Home in Central Virginia? (Part 3 of 5)

Phase 2 (2 or more months), also known as design development, takes these high-level concepts and starts creating ...
Thinking of Building a Luxury Home in Central Virginia? (Part 2 of 5)

Thinking of Building a Luxury Home in Central Virginia? (Part 2 of 5)

Phase 1 (1 or more months) of the design process, known as schematic design, is a discovery period for us and you. ...
No results found.

Discover more from The Gaines Group Architects

Subscribe now to keep reading and get access to the full archive.

Continue reading