Decisions made during construction will impact indoor air quality for years to come.

Feb 28, 2014

We spend a lot of time thinking about the health impacts of the building when designing an energy-efficient home. The ventilation rate needs to be designed and the materials used should be selected with care.

Then construction starts and it is cold outside. The next thing you know there is a portable heater sitting in the future living room. These machines are terrible for air quality for those building your project. Fuel oil off-gassing can have serious health impacts. The chemicals from the burn process can be absorbed by wood and drywall in your project and held until the project is finished.

Here is a solution used on a project we designed to be LEED Certified to keep the burn process outside the building envelope while sending the heat to the inside of the building.

IMG_3677

From a report done by Michigan State University: Following tests of 18 types of portable, unvented heaters, Consumer Reports states that: “We calculated the concentration of four gases produced by these heaters — carbon monoxide, carbon dioxide, nitrogen dioxide, and sulphur dioxide — in a 10x12x8-foot room with normal ventilation. The levels of each gas were high enough to be a serious health hazard to high-risk groups, including pregnant women, asthmatics, people with cardiovascular disease, children, and the elderly. The levels we calculated for some pollutants may pose risks for healthy people.” 

Related Posts

Thinking of Building a Luxury Home in Central Virginia? (Part 5 of 5)

Thinking of Building a Luxury Home in Central Virginia? (Part 5 of 5)

Phase 4, known as construction administration, starts with dirt moving as construction begins. We stay available ...
Thinking of Building a Luxury Home in Central Virginia? (Part 4 of 5)

Thinking of Building a Luxury Home in Central Virginia? (Part 4 of 5)

Phase 3 (2 or more months), also known as construction documents phase, takes all the decisions and testing we ...
Thinking of Building a Luxury Home in Central Virginia? (Part 3 of 5)

Thinking of Building a Luxury Home in Central Virginia? (Part 3 of 5)

Phase 2 (2 or more months), also known as design development, takes these high-level concepts and starts creating ...
Thinking of Building a Luxury Home in Central Virginia? (Part 2 of 5)

Thinking of Building a Luxury Home in Central Virginia? (Part 2 of 5)

Phase 1 (1 or more months) of the design process, known as schematic design, is a discovery period for us and you. ...
No results found.

Discover more from The Gaines Group Architects

Subscribe now to keep reading and get access to the full archive.

Continue reading