Chesapeake Western Depot rough-in started
Progress is being made on the Depot project in downtown Harrisonburg, Va. The electricians and plumbers have started doing rough-in work and the HVAC install is scheduled to start today. The framing is mostly done in the two-story portion of the project. Work still needs to be done repairing the entrance stair and the entrance will need to be framed.
The Daily News Record also ran a story on the project this past week.